Site DNA site report · derby south · 4 aug 2026

Derby South

The largest published demand headroom in GB open grid data, beside a council-led innovation park with its own under-used substation. SE Derby: Sinfin, Infinity Park, the Rolls-Royce campus.

185 MVA
available headroom
270 MVA
firm capacity
GREEN
constraint status
3,127
parcels in 1.2 km
972
corporate titles
0
green belt / CA / art. 4
Verdict

Worth pursuing. The strongest paper case in GB open data: 185.1 MVA published at the BSP, no green belt or conservation constraint, and land that could carry a campus — a 51.6 ha parcel 233 m from the substation, buildable ground north and east, flood confined to the south-west quadrant.

One unknown decides it: the demand-connection queue is private, so the 185.1 may already be spoken for. A free NGED budget estimate settles that in ~10 working days. The assembly story is unusually simple — Derby City Council holds both sides of Sinfin Lane and Infinity Park: one landlord to talk to first, not thirty. Hallam Land on the zone's edge says a strategic promoter already rates the area.

The map — every layer, togglable

Derby South

185.1 MVA
available at the BSP · 3,127 parcels in 1.2 km
Rings 500 m / 1 km. Click parcels for INSPIRE id + area, substations for headroom. Red dot = BSP, black = primaries. Double-click to enable scroll zoom.
The site — parcels that could carry a campus
AreaFrom BSPINSPIRE idScreen
51.6 ha233 m27535254clear
12.8 ha117 m27646112clear
16.2 ha596 m27640228clear
13.7 ha706 m27615674clear
14.1 ha857 m57351683clear
14.8 ha1,192 m27443901clear
20.2 ha976 m62075271flood 2/3

Every registered parcel over 10 ha in the study area. A campus needs roughly 10–20 ha contiguous; seven holdings here pass that bar on their own, six clear of flood zone. Screen = flood / green belt test at the parcel centroid — boundary overlaps need the parcel-level check. INSPIRE id is not a title number; the owner of each parcel is a £7 official copy away, listed under next moves.

Layers
Power
SubstationRoleFirmAvail.RAG
Derby South 132/33kVBSP270185.1green
Infinity Park 33/11kVprimary2317.3green
Allenton 33/11kVprimary3813.0green
Sinfin Lane 33/11kVprimary18.84.1amber

MVA. NGED LTDS Capacity Heatmap, 27 Jul 2026 cut. A campus connects at 33/132kV — the BSP figure is the one that matters. Headroom is a planning figure, not a connection offer — and the demand-connection queue is not public, so any published figure can already be spoken for by an application the open data cannot see. Treat 185.1 as unverified until a free NGED budget estimate confirms it; that is the first next step, not a formality.

Planning — 2 km box
  • ✓Green belt — none
  • ✓Conservation area — none
  • ✓Article 4 direction — none
  • ✓Tree preservation zone — none
  • ✓Agricultural land — Grade 3 / urban, no Grade 1–2 (3a/3b split unverified)
  • ▲Flood 2/3 — blankets the SW quadrant (Sinfin Moor→Trent). Buildable land is N and E of the BSP.
  • ▲Boulton Moor SSSI — touches eastern edge; buffer, not blocker
  • ✓Brownfield register — ex-Rolls-Royce Main Works 8.73 ha pending, Elton Rd 2.08 ha
Ownership — who holds the land
OwnerTitlesHoldingSignals
Derby City Council160+Infinity Park, both sides of Sinfin Lane, Sinfin Moor — the assembling authority—
Rolls-Royce PLC / group12Victory Rd + Wilmore Rd campus, both sides of the BSP—
Western Power Distribution (E Mids)28The substation + adjoining land — the DNO owns the expansion ground—
Infinity Park Derby Mgmt + CCPEPF UK Acq. 33The park + land SW of Infinity Park Way (institutional — verify beneficial owner)—
Hallam Land Management1West of Deepdale Lane — strategic promoter on the zone's edgepromoter
Clowes / Hortons' / Miller / Wimpey / D. Wilson~15Developer + estate land, Victory Rd and Sinfin Moor fringe—
Severn Trent / Cadent / Fulcrum5Water + gas operational land in-zone — services present—

437 companies hold titles in-zone; 82 matched the Companies House signals layer; 8 flagged (charges: Euro Garages, Done Bros, Taylor Wimpey; late filing: Cornerstone). No distressed owner on a strategic plot. HMLR CCOD Jun 2026. Polygon↔title attribution needs a £7 official copy per title — not guessed here.

Next moves — in order
#MoveSourceRouteTier
1Budget estimate, 50–150 MW at Derby South — the one check that verifies the 185.1 against the live queueNGEDFree application, ~10 working daysFree
2Official copies on the five strategic titles — pins each campus-scale parcel above to its ownerHMLR£7 per title, £35 totalPaid
3Serviced-plot availability at Infinity Park; freeport incentive stackDerby City CouncilDirect enquiryPaid
4Agricultural grade 3a/3b split on the greenfield parcelsNatural England ALCPost-1988 detailed survey where published; site survey otherwisePaid
—Owner accounts, charges, filing history — 437 in-zone companies, 82 matched, 8 flaggedCompanies HouseAlready in this reportFree